News: brad.haugaard@gmail.com   •  Restaurants   •  Library Catalog   •  Library Activities  •  History   •  Facebook / X/Twitter / RSS

Concrete Poured for 210 Freeway Bridge


Gold Line Extension spokesman Habib Balian writes: 

Skanska is nearing completion on the 18-hour concrete pour for the I-210 Gold Line Bridge. Since 11:00 p.m. last night (when the eastbound lanes of the I-210 Freeway were fully closed) crews have been non-stop placing 2,100 cubic yards of concrete into the superstructure and main outrigger beam that crosses the freeway. More than 200 truckloads have accessed the site from the freeway, center median and southern shoulder to strategically place what amounts to 50 typical swimming pools of concrete.
 
This important activity was planned over several months and took the coordination of multiple agencies. Skanska has done an outstanding job in the design and execution of this activity that went off smoothly and will result in the architectural elements of the superstructure permanently formed on the exterior of the structure.

- Brad Haugaard

No comments:

Post a Comment