News: brad.haugaard@gmail.com   •  Restaurants   •  Library Catalog   •  Library Activities  •  History   •  Facebook / X/Twitter / RSS

210 Bridge Foundation About to be Drilled



Mr. Crane being assembled to drill foundations.

The foundation for the 210 bridge over the eastbound lanes near Santa Anita will be drilled over the next four weeks, according to a press release from Gold Line Spokesman Habib Balian.
In the image you can see a large drill rig and crane are being assembled on the south side of the freeway. This is the location of the first of three 110 foot deep, 11 foot in diameter foundations. The other two are located in the center median of the freeway.  
"Each foundation will take approximately six days to drill and cast. We anticipate drilling the first foundation next week, followed by the installation of the reinforcing steel cage, concrete placement and testing the following week. This schedule is dependent on receiving final approval from Caltrans this week. During these activities, partial and full eastbound lane closures are planned (full closures occur late at night to minimize traffic delays)."
- Brad Haugaard

No comments:

Post a Comment